No. Document Category Deadline Re-upload deadline (days) Daily penalty points Maximum penalty points Last submission deadline Template
1 IAD || Impact Attenuator Data All March 18th 2022 7 15 De-registration March 25th 2022 FSG
2 SES || Structural Equivalency Spreadsheet All March 18th 2022 7 15 De-registration March 25th 2022 FSG
3 SE3D || Structural Equivalency 3D Model All March 18th 2022 7 15 De-registration March 25th 2022 FSG
4 ESF || Electrical System Form EV April 1st 2022 7 15 De-registration April 8nd 2022 FSG
5 HSD || Hybrid System Description HV May 6th 2022 - 10 No Limit May 20th 2022 FSAA
6 BPES || Business Plan Executive Summary All June 17th 2022 - 5 50 July 1st 2022 FSAA22 Handbook*
7 DSS || Design Spec Sheet All June 17th 2022 - 5 100 July 8th 2022 FSAA
8 EDR || Engineering Design Report All June 17th 2022 - 5 100 July 8th 2022 FS Rules 2022*
9 BPPV || Business Plan Pitch Video All June 24th 2022 - 5 50 July 8th 2022 FS Rules 2022
10 BPDD || Business Plan Deep Dive All June 24th 2022 - 5 50 July 8th 2022 FSAA
11 VSV || Vehicle Status Video All  July 22nd 2022  3  15  De-registration  August 5th 2022 FS Rules 2022
12 CRD || Cost Report Documents All  July 29th 2022  -  10 70  August 5th 2022 FSG
13 DR || Drivers' Registration All  August 9th 2022  -  15  No Limit  August 23rd 2022 FSAA
14 ESOQ || Electrical System Officer Qualification EV  August 1st 2022 - 10 De-registration  August 15th 2022 FS Rules 2022
15 TMRF || Team Member Registration Form All  August 9th 2022  -  15   No Limit  August 23rd 2022 FSAA

° All Deadlines are until 13:00 CE(S)T
°° Penalty points that are deducted from the Overall score
°°° IAD, SES, SE3D and ESF to be uploaded directly to FSG website/system (account needed on FSG Website)